Tech On New Energy: hard work to accelerate the spring running horsepower all open construction busy
2024.03.14

Machines roar, cranes hang high, vehicles shuttle... At the beginning of the Year of the Dragon, the Zhongxin Zhidi (Zhenjiang) high-end equipment Manufacturing Industrial Park, located on Beishan Road, Zhenjiang Economic Development Zone, is a busy scene, full of new vitality of high-quality development of industrial projects.

微信截图_20240314152236.png

The reporter saw that outside the factory building of Zhenjiang Tech On New Energy Co., LTD. (hereinafter referred to as "Tech On New Energy"), a huge robotic arm waved in the air, accurately placing tons of filter materials such as activated carbon and quartz sand in a predetermined position to facilitate the efficient use of pure water equipment after it was put into operation; In the factory, the staff shuttle between all kinds of machinery, their hands move quickly on the equipment, installation, debugging, testing... Every movement is precise and skilled, the roar of the machine, the tapping of the tool, the friction of the metal one after another, played a spring struggle movement.

"It can be said that everything is ready now, and after all equipment commissioning is completed, the production line will enter trial production." Zhu Wanchao, head of the management department of Tech On new energy enterprise, said happily that the enterprise passed the project filing in July last year, the main business is the new energy vehicle power battery housing, the total investment of the project is 120 million yuan, covering an area of 10,000 square meters, the construction began in mid-October last year, and the installation progress of the first production line has exceeded 90%. It is expected that the production line will be able to "run" in mid-March this year.

微信截图_20240314152450.png

Steel strip rolling, surface treatment, electrodeposition, washing, heat treatment, slitting, stamping, packaging... As the production line of this project is the first production line of new energy vehicle power battery housing independently designed and produced according to demand, higher requirements are put forward for installation accuracy and process flow. In order to ensure that the project is completed on time, the company closely monitors the construction schedule and details the construction period plan to every day. "Our payment to the supplier also follows the construction progress, and if a link is stuck, the project team will immediately start to fight to ensure that every node can complete the task on time." Project leader Zeng Lingke said.

It is understood that the park distribution room was originally equipped with four transformers of 2500 kVA, due to the large demand for electricity after the completion of the project, if directly from the distribution room cable access, not only the cost is too high, and the power loss is also large, from the efficiency, cost considerations are not the optimal choice. After the enterprise feedbacks the power connection problems to the economic development zone, the project service team understands the situation at the first time, takes the initiative to coordinate the docking of the enterprise, power supply, and the park, and conducts joint research and analysis to crack the engineering problems.

微信截图_20240314152544.png

"In the end, we came up with a plan to kill two birds with one stone, the park stopped two transformers, two transformers at the enterprise's own expense, the two high-voltage lines of the distribution room are directly connected to the plant, so that the plant can not only meet the current demand for electricity, even if the production line is upgraded in the later stage, it can also increase capacity on this basis." Zeng Lingke told reporters that with the full cooperation of the power supply department, the park carrier and the functional departments of the economic development zone, the project was completed very smoothly.

While grasping the construction of the production line, the handling of various formalities and licenses is also continuing to advance. Thanks to the proactive service of the economic development area and functional departments, we provide enterprises with full process and nanny service, and help enterprises handle relevant procedures such as registration, environmental assessment, energy assessment, safety assessment, and health assessment, which effectively guarantees the smooth progress of the project. "During the process, we received a lot of help from the recruitment department, the project service department and the park management office." Zhu Wanchao sighed, the economic development zone even intimate for the enterprise to provide 5 sets of housing, free for employees to use for two years, in the face of such an excellent business environment, their own business is more energetic.

Zhu Wanchao introduced that the project settled in Zhenjiang Economic Development Zone, but also let the enterprise closer to raw materials and customers, transportation logistics costs significantly reduced, and the work docking with many key customers such as Ningde Times, billion Wei Lithium energy, BYD, aerospace lithium power is also more efficient. He said that the company is expected to achieve mass production in April this year, to achieve annual sales of 100 million yuan, the second half of the year, the project's new production line will be built one after another, all completed and put into operation, annual sales can reach 350 million yuan.

Source: Junction News